GC01 standard project progress in October 2024
一、Bade (Southern Section) Work Area:
(1) A total of 337 foundation piles on Jiande Road and new roads were completed in November 2020.
(2) A total of 66 pile caps on Jiande Road and new roads have been completed in June 2021.
(3) A total of 61 RC piers on Jiande Road and new roads have been completed in August 2021; a total of 5 steel piers have been completed in September 2021.
(4) A total of 62 cap beams on Jiande Road and new roads have been completed in May 2022.
(5) A total of 16 spans of cast box girder bridge decks have been completed on Jiande Road and newly opened roads.
(6) The construction of 64 Xixuan concrete U-shaped beams on Jiande Road and newly opened roads has been completed in May 2023.
(7) A total of 7 span steel box beams have been hoisted on Jiande Road and newly opened roads.
(8) New road_Excavation, backfilling, and steel lining installation of the No. 4 working well of Jianguo Road Co-management.
(9) Common pipeline (Jianguo Road ~ Rende Road) internal finishing and threading of manholes.
(10) Piliao River box culvert steel bar processing.
(11) Outflow control IN-04 gutter (4k+880~4k+900) wall formwork assembly and inspection, concrete pouring.
(12) The G01 station body and connecting passages have been hoisted, and the roof waterproofing and exterior wall waterproofing are being carried out; the entrance and exit of G02 station are currently undergoing mud work and roof waterproofing work.
二、Luzhu, Dayuan (North Section) Work Area:
(1) Zhongzheng North Road Work Area B (Zhongzheng North Road, Luzhu District, Nanzhu Road~Zhongzheng Road Bridge), Work Area C (Zhongzheng North Road~Nangong Road, Luzhu District), D-1 Work Area (Luxing Street-Nanqing Road~Nan Gong Road Section 2), Nankan Road Section 2 D Work Area (Nanqing Road~Shanlong Gas Station), E Work Area (No. 532, Nankan Road Section 2~Kengguo Intersection) and F Work Area (Kengguo Road-G31~G32 Station) 1,458 foundation piles have been completed in May 2022.
(2) A total of 249 pile caps on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kangguo Road have been completed.
(3) Pier construction continues on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kengguo Road, with a total of 247 piers completed.
(4) Zhongzheng North Road, Section 2 of Nankan Road, Section 2 of Sanmin Road and Kangguo Road continue to carry out cap beam construction, and a total of 225 cap beams have been completed.
(5) A total of 63 cross-span cast box girder bridge decks have been completed on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kengguo Road. Currently, DU14-04 triangular bracket material lifting and DU14-14 breast wall are being carried out. Formwork disassembly, appearance modification of DU14-10 bridge and installation of DU14-09 (P14-29) anti-fall bridge.
(6) A total of 200 Xixuan concrete U-shaped beams have been hoisted on Zhongzheng North Road, Section 2 of Nankan Road, Section 2 of Sanmin Road and Kangguo Road.
(7) A total of 64 span steel box beams have been hoisted on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kengguo Road.
(8) The entrance and exit of G13 station and the station body are currently undergoing the installation of the platform glass curtain frame and the aluminum plate on the roof layer; the entrance and exit of G13a station are currently undergoing the assembly of the cushion formwork on the third floor of the station entrance; the entrance and body of G14 station are currently undergoing the installation of the station entrance and exit. The construction of sound-absorbing wall panels on the first floor and the station hall floor; the entrance and exit of G31 station are currently under construction to restore the dustproof net and the concrete pouring of the elevator and escalator pit walls at the platform level of the station; the entrance and exit of G32 station are currently under construction Carry out station fire alarm system piping, C-shaped steel installation and locking.
三、As of October 31, 2024, the progress of the GC01 bid was 80.43%.
GC02 standard project progress in October 2024
一、 Structural backfilling operations, support removal operations, and safety monitoring operations in the south excavated section.
二、 G03 station structure construction, shield tunnel excavation, fence painting and renovation, and safety monitoring operations.
三、 G04 station continuous wall construction, intermediate column construction, excavation and support system construction, site treatment construction, fence painting and renovation, safety monitoring work.
四、 VS4 ventilation shaft excavation and support system construction, pipe power project advancement, fence painting and renovation, and safety monitoring operations.
五、 G05 station excavation and support system construction, fence painting and renovation, and safety monitoring operations.
六、 VS5 ventilation shaft structure construction, fence painting and renovation, and safety monitoring operations.
七、 G06 station earth excavation and support system construction, entrance and exit structure construction, fence painting and renovation, and safety monitoring operations.
八、 VS6 ventilation shaft structure construction, fence painting and renovation, and safety monitoring operations.
九、 Excavation and support construction of the covered section of the brown line maintenance track, and fence spray painting and renovation.
十、 Relevant construction plan submission, detailed design mid-term/final review, BIM (Building Information Model), PMIS (Project Management Information Management System) construction.
十一、As of October 3, 2024, the actual progress of GC02 bid is 40.43%.
GC03 standard project progress in October 2024
一、 The detailed designs of each station and the hidden shield tunnel are submitted for review, BIM construction and PMIS modules are updated, and relevant plans/construction drawings of each station, the northern excavated section and the hidden shield tunnel are submitted.
二、 Construction of B4F SRC columns and side walls of G07 station; B5F excavation.
三、 B7F independent column steel bar binding and lane construction in the G08 station soil opening area; B4F column wall steel bar binding in the station body area.
四、 G09 station B3F column wall steel bar binding.
五、 G10 station rail platform substructure, corridor floor, side wall and roof construction; entrance and exit excavation support work.
六、 Construction of the north-south well structure, platform and rail bed substructure of the G11 station track layer; construction of the partition wall of the entrance and exit corridor, construction of the mezzanine wall and 1F version structure, construction of the entrance and exit expansion area structure; construction of the station body and entrance and exit Installation of electrical, water systems and air ducts and pipelines in the hall, and construction of sound-absorbing walls.
七、 Construction of the platform substructure and rail bed at the track level of the G12 station, construction of the buffer zone for the connecting passages at the north and south well crossings; painting work at the entrance and exit A and the emergency stair crossing, and construction of the shaped roof at the ground floor of entrance and exit A; station and Installation of electrical, water systems and air ducts and pipelines at entrance and exit halls.
八、 China's No.1 submarine shield machine excavation operation (G09~G08); No.2 submarine shield machine opening inspection operation (G10~G09); G08 0K+453 gear changing area site improvement operation.
九、 Small round tunnel equipment dismantling and cleaning operations, uplink invert and walkway construction; structural construction of the north excavated section.
十、 As of October 31, 2024, the GC03 bid has been implemented at 59.85%.
GC05 standard project progress in October 2024
一、 Elevator project: We are currently handling the mid-term and final design and manufacturing operations of the northern section of the station opened to traffic and the Beiji Plant.
二、 Elevator and escalator project: We are currently handling the mid-term and final design and manufacturing work for the northern section of the station that is open to traffic.
(1). G13 station escalator glass and handrail installation work.
(2). Installation of safety guardrails and step chain connection work on the escalator at G13a station.
(3). G13a station escalator skirt panel installation work.
三、As of October 31, 2024, the implementation progress of the GC05 bid is 8.5839%.
GM01 standard project progress in October 2024
The Taoyuan MRT Green Line GM01 standard project includes electromechanical systems, track engineering, civil construction of the North Machinery Plant and main substation, and other electromechanical projects.
一、 Mechanical and electrical system:
(1). Each subsystem is currently handling mid-term and final design work.
(2). Beiji Plant, G13~G13a station communication system, monitoring and data acquisition system, power supply system, traffic monitoring system and platform door system cable and equipment installation engineering construction.
(3). Manufacturing of MRT Green Line trains.
二、 Track engineering:
(1). Floating and pedestal track construction between Lucing Street and G14 stations (up and down).
(2). Track construction of the special track switch group between G14~G31 stations.
三、 Beiji Plant Civil Engineering Project:
(1). Structural decoration work of the North Main Substation, Management Center, Main Maintenance Shop, and Parking Depot.
(2). Construction of retaining wall in machine plant.
四、 The GM01 target progress as of October 31, 2024 is 36.46%.