Overview of track construction progress

Overview of Three-core and Six-Line Track Construction

MRT Airport Line
MRT Green Line
MRT Brown Line
MRT Sanying extends Bade
MRT Green Line extends Zhongli
Taoyuan Railway Underground
              

Writing reports

The report is completed and sent to the Ministry of Transportation for review

The Ministry of Transportation and Communications passed the review and transferred it to the Executive Yuan for renewal.

Approved by the Executive Yuan

Writing reports

The report is completed and sent to the Ministry of Transportation for review

City plan changes sent to city council for review

The environmental impact assessment was reviewed and approved by the Ministry of Environment

The Ministry of Transportation and Communications passed the review and transferred it to the Executive Yuan for renewal.

Approved by the Executive Yuan

Announcement

Winning the bid

construction stage

Open to traffic

Feasibility study stage

Comprehensive planning stage

Project bidding

Project nameCurrent stageProgress description
MRT Airport LineOpen to traffic2017/3/2 Open to traffic operation.
MRT Green LineConstruction stageThe overall plan progress is 59.96%, 0.44% ahead of schedule.
MRT Brown LineProject bidding stageThe project management consultant and engineering supervision entrusted technical services were awarded on May 15, 2024.
MRT Sanying extends Bade Comprehensive planning stageThe National Development Council agreed to support it at the review meeting on June 11, and the revised report was sent to the committee for further review on June 13.
MRT Green line extends ZhongliProject bidding stageThe project management consultant and engineering supervision entrusted technical services were awarded on March 8, 2024.
Taoyuan railway undergroundConstruction stageSponsored by the Railway Bureau of the Ministry of Transport, bidding for the main project will begin in April 2022.