GC01 standard project progress in May 2024

一、Bade (Southern Section) Work Area:
(1) A total of 337 foundation piles on Jiande Road and new roads were completed in November 2020.
(2) A total of 66 pile caps on Jiande Road and newly opened roads were completed in June 2021.
(3) A total of 61 RC piers on Jiande Road and newly opened roads were completed in August 2021; a total of 5 steel piers were completed in September 2021.
(4) A total of 62 cap beams on Jiande Road and newly opened roads were completed in May 2020.
(5) A total of 16 spans of cast box girder bridge decks have been completed on Jiande Road and newly opened roads.
(6) The construction of 64 Xixuan concrete U-shaped beams on Jiande Road and newly opened roads was completed in May 2023.
(7) A total of 7 span steel box beams have been hoisted on Jiande Road and newly opened roads.
(8) New roads_ (Jianguo→Rende)_shared management and open excavation.
(9) New road (Guangxing Road)_Co-management working shaft sinking and excavation.
(10) New road (Jianguo Road)_ Rainwater box culvert entry/reach working shaft sinking and excavation.
(11) G01 station and G02 station station body and connecting passages have been hoisted, and metal wall panels and curtain walls have been constructed.
(12) The entrances and exits of G01 station and G02 station are currently undergoing exterior wall waterproofing and roof waterproofing work.

二、Luzhu, Dayuan (North Section) Work Area:
(1) Zhongzheng North Road Work Area B (Zhongzheng North Road, Luzhu District, Nanzhu Road~Zhongzheng Road Bridge), Work Area C (Zhongzheng North Road~Nangong Road, Luzhu District), D-1 Work Area (Luxing Street-Nanqing Road~South Gong Road Section 2), Nankan Road Section 2 D Work Area (Nanqing Road~Shanlong Gas Station), E Work Area (No. 532, Nankan Road Section 2~Kengguo Intersection) and F Work Area (Kengguo Road-G31~G32 Station) 1,458 foundation piles were all completed in May 2011.
(2) A total of 249 pile caps on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kengguo Road have been completed.
(3) Pier construction continues on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kengguo Road, with a total of 247 piers completed.
(4) Construction of cap beams continues on Zhongzheng North Road, Section 2 of Nankan Road, Section 2 of Sanmin Road and Kangguo Road, with a total of 224 cap beams completed.
(5) Zhongzheng North Road, Section 2 of Nankan Road, Section 2 of Sanmin Road and Kangguo Road have completed a total of 63 span cast box girder bridge decks. The cast box girder DU14a-01-1 unit steel structure bridge deck is currently in progress. , side formwork laying; DU14-04 unit (steel structure three-span P14/15-8~P14/15-11 steel bar binding group.
(6) A total of 196 Xixuan concrete U-shaped beams have been hoisted on Zhongzheng North Road, Section 2 of Nankan Road, Section 2 of Sanmin Road and Kengguo Road.
(7) A total of 52 span steel box beams have been hoisted on Zhongzheng North Road, Nankan Road Section 2, Sanmin Road Section 2 and Kangguo Road. Steel box beam production and hoisting operations are currently ongoing.
(8) The entrance and exit of G13 station are currently undergoing metal curtain construction, interior wall panel construction and platform cushioning work; the entrance and exit of G13a station are currently undergoing metal curtain construction, door and window engineering and painting work; the entrance and station body of G14 station are currently undergoing construction Door frame engineering and roof panel engineering are currently in progress; G31 station 4th floor cushion and 5th floor column wall construction are currently underway; G32 station entrance and exit are currently undergoing station body hoisting, electrical pipeline construction and connecting channel deck construction.

三、 As of June 30, 2024, the progress of the GC01 bid was 78.99%.

G31 station entrance and exit roof steel bar binding

G31 station entrance and exit roof steel bar binding

G31 station entrance and exit roof steel bar binding
DU14-08 down line parapet mold transfer
G32 station hoisting
Concrete pouring of the restored edge stone base of the central dividing island in Section 2 of Nankan Road
Construction of electrical pipelines and drainage pipelines at G13a station

B

MRT
Brown Line

MRT Brown Line MAP

LB

MRT SanYing
Extend to Bade

MRT SanYing Extend to Bade MAP

GE

MRT Green Line
Extend Zhongli

MRT Green Line Extend Zhongli MAP

R

Taoyuan Railway
Underground

Taoyuan Railway Underground MAP